Madrid Metro Line 11

Madrid Metro Line 11 is undergoing one of the most ambitious transformations in the history of the city's underground network. From a relatively short local line connecting Plaza Elíptica and La Fortuna, it will become a major corridor crossing the capital from south to north, known as Madrid's Great Diagonal. The project aims to significantly improve connections, relieve pressure on other lines and offer more efficient public transport, with particular benefits for Valdebebas residents.

Updated: 13 October 2026

Madrid Metro Line 11 in Valdebebas

Latest updates

Six consortia compete for the extension to Valdebebas Norte

On 9 October 2026, MadridPress reported that six consortia were interested in a tender split into two lots, with a total investment of €880.6 million.

Two construction contracts

  • Mar de Cristal–Hospital Enfermera Isabel Zendal: a 39-month construction period and around €580 million.
  • Hospital Enfermera Isabel Zendal–Valdebebas Norte: a 32-month construction period and around €300 million. Both lots are intended to proceed simultaneously.

The new Madrid Metro Line 11

Madrid Metro Line 11
  • Northern section (Mar de Cristal – Valdebebas) : The project covers 7.2 km and four new stations: Ifema-Cárcavas, Ciudad de la Justicia , Hospital Isabel Zendal and Valdebebas Norte. Interchanges will be provided at Mar de Cristal (Lines 4 and 8) and Aeropuerto T4 (Line 8 and Cercanías).
  • Central section (Plaza Elíptica – Conde de Casal – Mar de Cristal) : This section is currently under construction and prompted controversy over tree felling in Madrid Río. It will connect key locations such as Atocha and the M-30 corridor, aiming to relieve pressure on Line 6.
  • Southern section (Cuatro Vientos – Conde de Casal) : This section will extend the current line from La Fortuna to Cuatro Vientos and, in the future, towards Conde de Casal, improving connections with south-western Madrid.
  • The announced target is to complete construction of the northern section in 2030.
  • The route allows for potential future stations at Cristalia and next to Valdebebas Shopping; these are separate from the four new stations in this extension.

The impact of Line 11 on Valdebebas

  • Improved connections : Valdebebas will move from relying mainly on commuter trains and buses to having a direct Metro connection. This will greatly improve access to the rest of the city, including central Madrid and other key areas.

  • Direct airport access (T4) : One of the main benefits will be the direct connection to Terminal 4 at Barajas Airport. It will benefit Valdebebas residents and position the neighbourhood as a strategic location for professionals and businesses connected with airport activity.

  • Connections to key locations : The line will connect Valdebebas with Hospital Enfermera Isabel Zendal and Ciudad de la Justicia , improving access for workers and users of these important services.

  • Shorter journey times : Journey times are expected to fall significantly, saving Valdebebas residents considerable time on their daily trips.

  • A boost to urban development : The arrival of the Metro often stimulates development and increases property values around stations. This could further strengthen Valdebebas's growth as a modern, well-connected district.

  • Sustainable transport : By providing an efficient public transport alternative, Line 11 will help reduce private car use, traffic congestion and CO2 emissions in the area.

Madrid Metro Line 11 and its extension to Valdebebas will be a key part of the neighbourhood's future development, offering new transport options and connecting it directly with the capital's main activity hubs.

Useful links

Disclaimer

  • This website/project is not affiliated with, associated with, authorised by, endorsed by or officially connected in any way to Metro de Madrid or any of its subsidiaries or affiliates.
  • Any trademarks or copyrighted material on this website/project are used solely for informational and commentary purposes and are considered "fair use" under copyright law. No infringement of intellectual property rights is intended.
  • If you own any trademarks or copyrighted material used on this website/project and believe their use does not comply with the principle of "fair use", please contact us so we can review it.

Frequently asked questions about Line 11 in Valdebebas

Will Line 11 reach Valdebebas?

Yes. The project out to tender will connect Mar de Cristal with Valdebebas Norte via Ifema-Cárcavas, Ciudad de la Justicia, Hospital Isabel Zendal and Aeropuerto T4.

What improvements would Line 11 bring to the neighbourhood?

The new Metro connection could reduce journey times, improve airport access and strengthen connections between Valdebebas and other activity hubs in Madrid.

When will the extension be completed?

According to the information published on 9 October 2026, construction of the Mar de Cristal–Valdebebas Norte section is targeted for completion in 2030. This estimate depends on contract awards and construction progress.